RACINE A Wisconsin Department of Transportation (WisDOT) project team will soon be considering whether to schedule the replacement of the Highway 38 (Northwestern Avenue) bridge over the Root River into a single construction season or spread it out over two years. The work would start in 2024.

Regardless of the decision, motorists on the citys far northwest side will see delays and possibly detours for many months. The six-lane bridge carries more than 25,000 vehicles per day.

The 60-year-old bridge spans the river just downstream from the Horlick Dam. Traffic feeds onto the bridge from County Highway MM and Northwestern Avenue to the west, and from Northwestern Avenue, Rapids Drive and North Green Bay Road to the east.

Tuesday afternoon, about 100 people crowded into a gym at a WisDOT-hosted public input meeting at the Cesar Chavez Community Center, 2221 Douglas Ave., to view easel-mounted aerial photos depicting how traffic patterns would be affected by the project. WisDOT engineers and designers mingled about to take questions.

Visitors were invited to fill out comment forms at the meeting or submit comments online by next Tuesday, May 2. Email: justin.suydam@dot.wi.gov.

Were working on improving traffic flow by adding an extra (westbound) lane on the north side (of the bridge), said Janet Cannon, a WisDOT team member.

The project will also reconfigure the Highway 38 and Rapids Drive intersection, replace the pavement between County Highway MM and Rapids Drive, install new traffic signal equipment at Rapids Drive and add sidewalks and wider shoulders to accommodate bicycles.

The project overview map can be downloaded by clicking the button.

The first alternative would close the bridge to all traffic while the structure is removed and replaced; the new pavement and sidewalks completed, and the traffic signals installed. Traffic would be detoured away from the bridge crossing via Highway 31 and County C (Spring Street).

The reconstruction work would begin in the spring of 2024 and take about a year.

Justin Suydam, WisDOT project manager, said the estimated price tag is about $6 million.

The single construction season alternative for the Highway 38 bridge had originally been in the works with the replacement taking place this year (2023). The project was delayed, however, by the removal of a natural gas line and fiber optic cable lines across the bridge plus objections to the full closure.

In the second alternative, the north side of the bridge would be constructed in the first year (2024) and the bridges south side would be constructed in the second year (2025). The bridge would be restricted to single-lane local traffic in each direction. In addition, some left turns in the area would be prohibited and the lane reductions could cause delays.

Some types of traffic would be sent on alternative routes around the bridge.

Transporting 150-foot bridge girders to the construction site would require temporary roadway closures at times.

In both project timetables, construction within the Root River could not take place during certain times of the year so as not to interfere with spawning trout and salmon.

WisDOTs Suydam said the two-year staged project timeline would add about $2 million to the project bringing the price tag to about $8 million.

Pasquale Infusino, who operates a restaurant and banquet hall on nearby Rapids Drive, was all-in on the two-year option. He presented the WisDOT team with copies of petitions that he said held about 1,500 signatures. The signatures were collected at his business and other area locations over the past several weeks.

Its gonna cripple us just like having another (COVID-19) virus, Infusino told the Racine County Eye. Replacing this bridge half at a time is the way to go. Its still complicated, but it would help us tremendously.

Infusino said from talking with customers he learned that 65% of his traffic comes from the other side of the bridge.

But, Infusino added, the inconvenience isnt borne by just his restaurant.

Youve got school buses that use that bridge. People use it to get back and forth from work. Its just a mess, he said.

Other residents told WisDOT team members of concerns they had about a long-term bridge closure sending additional traffic to other nearby roadways and intersections, such as North Green Bay Road and Four Mile Road in Caledonia.

Maxwell Love, City of Racine communications specialist, attended the Tuesday meeting. He later provided a statement.

The Mayor of Racine heard concerns from local businesses and residents regarding the Highway 38 bridge construction project, the statement read. He requested that the Wisconsin Department of Transportation (WisDOT) reinitiate the community engagement project.

In addition, the statement said that Mayor Cory Mason has spoken with Transportation Secretary Craig Thompson about the bridge project issue and directed various city departments and staff to engage with the process.

The mayor has not suggested a preferred construction alternative, according to the statement.

Suydam said the team will review the public response from Tuesday and submissions received through the May 2 deadline during the next few weeks.

WisDOT plans to hold another public meeting in a month or two to inform residents of its decision and disclose project details.

The Racine County Eye, which includes the Kenosha Lens, is your source for local news that serves our diverse communities. Subscribe today to stay up-to-date with local news.

Follow us on Facebook: Racine County Eye or Kenosha Lens, and Twitter to make sure you get the latest news.

Racine County Eye and Kenosha Lens Journalism that serves.

Like Loading...

View original post here:
Highway 38 bridge project: One year or two? WisDOT weighing ... - Racine County Eye