BRECKSVILLE - The project to refurbish and replace portions of the Wiese Road retaining wall is on pace to be completed by the end of November.

Workers finished the replacement of crumbling paved sections and the installation of several concrete structural panels Nov. 6.

At that time, the only large items that needed to be finished were the refurbishing of a guardrail on the lower portion of the wall and some painting work on the panels.

Weve still got a little bit of work to do, but not too much more, City Engineer Gerry Wise said. The work is being done by Suburban Maintenance and Construction Inc., which agreed April 16 to do the work for roughly $944,000.

The firm is under the supervision of Donald G. Bohning and Associates Inc., which agreed to manage the project for an original fee not to exceed $35,000.

Wise said the project is still on pace to cost less than the $1.32 million that it was originally expected to cost, based on preliminary estimates.

Contact Rozboril at (216) 986-6065

Follow this reporter on Twitter @rrozboril

Return to Brecksville home page

Read more:
Update on Brecksville's Wiese Road Retaining Wall project

Related Posts
November 20, 2012 at 4:48 am by Mr HomeBuilder
Category: Retaining Wall