John Penney jpenney@norwichbulletin.com, (860) 857-6965 jpenneynb

KILLINGLY Work on three Killingly school roofs is expected to begin later this month and be completed before students return in the fall.

On Wednesday, the towns Building Committee accepted the low bids submitted for the replacement of the Killingly Memorial School and for a partial roof replacement at the Goodyear Early Education Center. The committee did not accept bids for work at the Killingly Central School, though it is expected to do so on Monday.

All the bids were well under what we expected, Community Development Director Mary Bromm said. Thats likely due to companies not having a lot of these major projects scheduled for this summer.

A $1.01 million bid from Hartford Restoration Services was selected for the Killingly Memorial School work, while a $226,000 bid is expected to be awarded to the Cromwell-based Imperial Company Restoration Services.

Residents in February approved a $6.25 million bonding package for school roof and window work, with 70 percent of the cost expected to be reimbursed by the state. Bromm said the planned window replacements wont begin until next year.

That kind of work falls into a separate category that requires legislative approval for reimbursement funding, she said. We should get an answer back by July 2018.

If the final cost of the project is less than the approved bonding figure, officials will simply not bond the entire amount, though the full anticipated costs must have been previously approved by taxpayers.

All three roofs are more than 20 years old and past their recommended lifespan, said Paul Mailhot, supervisor of operations and maintenance for the school district.

"There's been deterioration from (ultra-violet) light and general wear-and-tear from snow and rain over the last two decades," he said. "The rubber membranes are pulling away and we're getting cracks that constantly need patching. Anytime there's a big storm, we're patching and repairing those areas so water doesn't seep inside the buildings."

Residents in February also approved spending up to $3.2 million for several projects at the community center, including exterior brick re-painting, bathroom and locker room renovations and window work.

A portion of that money about $1 million - would be set aside to replace the nearly 100-year-old pipes running through Town Hall. Another $1.8 million was approved for upcoming bridge and culvert replacement, half of which is reimbursable by the state.

Link:
Bids for work on Killingly school roofs 'well under' expectations - Norwich Bulletin

Related Posts
July 7, 2017 at 5:44 am by Mr HomeBuilder
Category: Window Replacement