Home » Office Building Construction » Page 60
Page 60«..1020..59606162..7080..»
 
    Portland, Ore.-based Hoffman Construction is a national    contractor that prides itself on using digital tools to    complete its projects.  
    So, in mid 2015, when it was planning to renovate a 10,000-sf    office space in Seattle, Hoffman challenged its interior    designer, Gensler, to take a similar approach that would    highlight Hoffmans digital integration and technical delivery    techniques.  
    With the help of a host of digital productsincluding SketchUp,    Revit, Faro, Navisworks, Cyclone, AutoCAD and CNCthe Building    Team designed the space in just four weeks and helped the    client build it in seven.  
    Hoffman is always looking to do the impossible in a possible    amount of time. Gensler saw us as innovators showcasing our    talents with this project, says Kevin Ryan, operations manager    and GM for Hoffman Construction in Seattle.  
    The focal point was the Think Tank, a 2,000-sf space that would    serve as the offices central hub. That space, according to    Jeroen Teeuw, Senior Associate at Gensler who was Lead Designer    on this design-build project, is clad in over 100 unique panels    that were fabricated from shop drawings produced by digital    scans. Fuller Cabinets in Eugene, Ore., supplied the panels,    which were fabricated by Straight-Up Carpentry in Oregon.  
    Photo courtesy of Heywood Chan    Photography.  
    Teeuw says that, before this job, Gensler had only rarely    employed digital scanning for interior projects. The scans, he    says, were accurate to the point where no tweaks to the design    were necessary. Hoffman had a lot of trust in us, he says.  
    Demolition started on Sept. 1, 2015, and included four weeks of    asbestos mitigation. Building started the first week October.    Hoffman wanted to occupy the building by Christmas,so we    had to identified what absolutely needed to be done in order to    satisfy the fire marshals and inspectors, recalls Ryan. The    Building Team stripped the floors, knocked down walls, and    installed new T-bar ceilings.  
    For the renovation, the Building Team broke up the shop    drawings into several packages, which Ryan says all but    eliminated material waste.  
    Hoffman achieved its goal, even though the office wasnt fully    completed until April 2016. The space includes conference rooms    and private offices, a central teaming area,    pantry/lounge/kitchen, open workspace, facilities space, and a    reception area.  
See more here:
Digital tools accelerated the design and renovation of one contractor's new office building - Building Design + Construction (press release)...
 
Category 
Office Building Construction | Comments Off on Digital tools accelerated the design and renovation of one contractor’s new office building – Building Design + Construction (press release)… 
        Southbrooke Medical Center is planned        just east of Valewood Drive on more than 5 acres of        undeveloped land on the south side of Immokalee Road in        North Naples.(Photo: Tim        Aten/Naples Daily News)Buy        Photo      
    Two new medical office complexes are planned off Immokalee Road    east of Interstate 75 in North Naples.  
    Southbrooke Medical Center is planned just east of Valewood    Drive on more than 5 acres of undeveloped land on the south    side of Immokalee Road. The proposed construction project    includes two nearly 20,000-square-foot buildings for medical    use, Collier County development records show.  
    Each of the identical one-story buildings is proposed to have    11 units ranging from 1,601 to 2,189 square feet, the site plan    shows. The inline buildings will both front Immokalee Road and    be built 30 feet apart by Naples-based Phoenix Associates of    Florida.  
    Ground is expected to be broken soon for Southbrooke Medical    Center. Construction will start once the project is 50 percent    pre-leased, said Bill Young, senior associate for CRE Consultants, who is    looking to sign medical and office tenants.  
    Were not too far off now, Young said. We have medical,    dental, general practice and office uses lined up.  
    The tree-covered acreage was rezoned in November 2015 from    estates residential to a commercial planned unit development    zoning district to allow the project to be built. A swath of    native foliage will be preserved between the rear of the    development and Autumn Oaks Lane, a residential street to the    south that runs parallel to Immokalee Road, the site plan    shows.  
    The sole entrance into Southbrooke Medical Center is proposed    from Immokalee Road to line up with the existing Executive    Drive on the north side of the road, plans show. Turn lanes off    Immokalee Road are proposed for both eastbound and westbound    traffic.  
    Plans also show that 210 parking spaces for the medical offices    will be divided between the north and south sides of the    buildings. Medical offices require one parking space for every    200 square feet of building compared with one for every 300    square feet of general office space, according to the countys    land development plan.  
      Equity Inc. recently broke ground for a freestanding office      building to be built on a corner lot on the north side of      Piper Boulevard near the intersection of Airport-Pulling and      Immokalee roads in North Naples. (Photo: Tim Aten/Naples Daily News)    
    An unrelated development project by Equity    Inc. recently broke ground on a 9,950-square-foot    freestanding office building to be built on a corner lot on the    north side of Piper Boulevard near the intersection of    Airport-Pulling and Immokalee roads.  
    The property at 1035 Piper Blvd. is on the corner of Cypress    Way East that was part of the parking lot space for the former    Naples Dinner Theater, which closed a decade ago after an    eight-year run. The new one-story commercial building will be    built between The Lockup self-storage building and a medical    office building with units for dentistry, dermatology, oral    surgery, prosthetics and weight loss.  
    Suites from 1,500 to 5,620 square feet are available for lease    in the proposed Piper Medical office building.  
    Declining vacancy rates in the area combined with the location    make this new build an unsurpassable opportunity for office or    medical tenants, according to a news release from Equity Inc.,    a full-service commercial real estate firm.  
         Sanctuary Nursery doubling in size  
    Pelican    Nursery closing, land to be redeveloped  
    Orangetree    Publix finally opens in Golden Gate Estates  
    4    or 5 restaurants planned for 2nd phase of Cameron    Commons  
    Have a local question? Email it with your name and city of    residence to intheknow@naplesnews.com.Tim Atens "In the    Know" is published every Monday and Wednesday.Like    In the Know on Facebook atfacebook.com/timaten.intheknow.  
    Read or Share this story: http://nplsne.ws/2nmGsad  
See the original post:
In the Know: New medical offices planned in North Naples - Naples Daily News
 
OMAHA, Neb.   
    The lead developer on the Turner Park East project, which    includes the area east of Midtown Crossing, said construction    should begin in spring of 2018.  
    Brad Schoenfelder, President of the Midwest Region for Ryan    Companies, said the company will spend the remainder of 2017    finalizing approvals and going through the city process to    begin construction.  
    Mutual of Omaha has acquired the properties to be included in    the Turner Park East project, and Ryan Companies will head up    the development.  
    "We're very experienced in urban redevelopment and the    challenges and the opportunities that come with that,"    Schoenfelder said.  
    Ryan Companies' plans include a 150,000 square foot office    building on the south side of Farnam, which will include    multiple tenants. On the north side of Farnam, the developers    are planning for a mixed-use development including a hotel    component, multi-family residential units and a city-owned and    financed parking deck.  
    "We just want to make sure that we're continuing to activate    the streets and how were doing that is more about residential,    hospitality," Schoenfelder said.  
    Schoenfelder said Ryan Companies is working with the homeowners    association at the remaining Twin Towers buildings, now named    The Condominiums at 3000 Farnam.
    They are also working with the Midtown 2050 group, which is    behind a proposed streetcar that would run from Midtown into    downtown Omaha and to the Creighton campus.  
Go here to see the original:
Turner Park East developers hope to begin construction in spring 2018 - KETV Omaha
 
The building also helped to shape the popular imagination about    the LAPD, through its appearances on the television show    Dragnet in the 1950s and in the more recent police procedural,    The Closer.    
     Mon March 27, 2017 - National Edition    Elizabeth Chou, Los Angeles Daily News  
      The Parker Center building as it stands now. Photo by Hans      Gutnecht LA Daily News SCNG    
    The Los Angeles Police Department's former headquarters, Parker    Center, will be demolished and replaced with a $483 million    office tower to house city employees under a plan approved by    the City Council.  
    The council voted 12-0 Friday to greenlight the Bureau of    Engineering's proposal to replace the eight-story Parker Center    with a 27-story tower. The first floor will include commercial    and exhibition space, according public works officials.  
    Preservationists from the Los Angeles Conservancy had been    advocating for the city to rehabilitate the building, at 150 N.    Los Angeles St., instead of demolishing it. But the council    last month denied giving it a historic-cultural monument    designation.  
    Those in favor of keeping the building intact pointed to the    complex history of the building, which served as the LAPD's    administrative building, with a jail and crime labs, from 1954    until 2009. That era represented both some of the controversial    chapters in the Police Department's relations with the    African-American community, as well as some of the improvements    and efficiencies achieved in the department.  
    The building was originally called the Police Administration    Building, but later renamed for Police Chief William H. Parker    when he died in 1966. Charles Manson, Sirhan Sirhan and the    Hillside Strangler were among the most notorious criminals    booked at the facility.  
    The building also helped to shape the popular imagination about    the LAPD, through its appearances on the television show    Dragnet in the 1950s and in the more recent police    procedural, The Closer.  
    Parker Center is the work of architect Welton Becket, who also    designed the Music Center and the Capitol Records building.  
    Councilman Jose Huizar said Friday the building should be    demolished because it is not a good example of Becket's work,    and its existence dismisses the history of the    Japanese-American community and businesses that were displaced    when Parker Center was built.  
    Some artwork from Parker Center will be preserved, including a    bronze sculpture by Bernard J. Rosenthal and a mosaic mural by    Joseph Young.  
    Huizar said funds are still being gathered to move ahead with    the demolition and office building project.  
    The existing building has structural deficiencies that make it    unsafe for use, and due to asbestos in the building, the    demolition would likely occur slowly, with the structure being    taken apart bit by bit, public works officials said in a recent    committee meeting.  
    The offices at the Parker Center site are expected to serve as    the first project in a larger plan to revamp the Civic Center    where City Hall sits. The council voted to begin studying a    Civic Center master plan that aims to bring more housing,    office and commercial space to the area, as well as better    integrating the Civic Center into the surrounding communities,    which include Little Tokyo, Chinatown, El Pueblo and the Arts    District.  
    For more information, visit http://url.ie/11pxi  
Continue reading here:
Iconic Police Headquarters Faces Demolition - Construction Equipment Guide
 
  The tower, designed by CBT Architects, will feature double the  traditional amount of vision glass in an elliptical, bevel-edged  frame.
    BostonSkanska USAs bid to build the most    sustainable block in Boston moves closer toward realization    with the development and construction services companys    topping out the office tower at 121 Seaport. Skanska is on    track to complete the 400,000-square-foot building, located in    the citys Seaport District in 2018.  
    The Seaport District is an old industrial area, close to CBD    downtown. Its on the way to be developed from something that    was really on the outside, not really used, into something that    is really hot, both for residential development, but also    specially for commercial development, Johan Karlstrom, CEO of    Skanska AB, Stockholm-based parent company of Skanska USA, said    during the companys first quarter 2016 earnings conference    call on May 12, 2016.  
    Reaching the top-out point at 121 Seaport, which also    encompasses approximately 50,000 square feet of retail space,    was no simple task. Skanska didnt take the easy route,    utilizing the unconventional up-down construction method, which    calls for building the foundation and frame concurrently.    Additionally, with a construction team of roughly 200    professionals, the company installed 3,400 tons of steel, put    in place 63,000 fasteners and set four 76-foot-long plate    girders to support the high-rises position above the Silver    Line Tunnel. There were certain issues at one point, when    excavation at the site uncovered remains of a wooden cargo ship    that had succumbed to the sea in the 1800s. Skanska temporarily    halted the project for an official archaeological    investigation, and later resumed activity toward the topping    out milestone.  
    The tower, designed by CBT Architects, will feature double the    traditional amount of vision glass in an elliptical,    bevel-edged frame not seen anywhere else in the area. The    building will be a model of sustainability as well. From the    get-go, we set out to create a building that will stand out    from the rest, and 121 Seaport is as striking as it is    efficient, Charley Leatherbee, head of Skanskas development    operations in Boston, said in a prepared statement. In line to    achieve LEED Platinum status, the highest level of LEED    certification, 121 Seaport will utilize a rain reclamation    system for filtering and reusing rainwater, and a chilled beam    mechanical system to decrease energy consumption. Ample natural    light and water-efficient plumbing fixtures will also be on the    buildings list of green attributes.  
    121 Seaport will join two existing developments to finish    Skanskas creation of Bostons most sustainable block. 101    Seaport, which Skanska sold for nearly a half-billion    dollars in 2016, is part of the trifecta. The    440,000-square-foot office building is home to Skanska and    counts the North American headquarters of accounting giant    PricewaterhouseCoopers as its anchor. The green block also    includes Watermark Seaport, a 300,000-square-foot residential    tower. All three projects help Boston maintain its high ranking    on the list of the greenest cities in North America. According    to the sustainable cities index produced by Arcadis, a top    global design and consulting firm, Boston holds fifth place,    coming in just ahead of San Francisco, the greenest city on the    West Coast.  
More here:
Skanska Tops Out on Green Office Building in Boston - Commercial Property Executive
 
Max Sullivan msullivan@seacoastonline.com  @MaxSullivanLive  
    HAMPTON Construction for a new Marriott hotel and office    building will soon be in the works on Exeter Road, as the    Planning Board approved the projects site plan and wetlands    permit.  
    The Planning Board made the approval at its March 15 meeting.    The hotel, a SpringHill Suites Marriott, and the office    building are slated to be built at 287 and 299 Exeter Road,    which is next to CRs Restaurant. The project is being put    forth by AG Hampton Hospitality.  
    The Marriott will have four stories, 104 rooms and    approximately 150 parking spaces with an internal driveway    connection to CRs, according to Planning Board meeting    minutes. The office building, which does not yet have a tenant    secured, will be 40,000 square feet with three stories and 204    parking spaces.  
    Units in the hotel will each have a living room and a bedroom    as well as refrigerators and microwaves, and exterior patio    areas will be available for guests. The hotel itself will not    contain a bar or restaurant. The building will feature pitched    roofs, clapboard siding and other bandings to give it a New    England colonial look.  
    The Planning Board voted unanimously to approve the wetlands    permit for the site, then voted 6-1 to approve the site plan.    Chairman Brendan McNamara voted against passing the site plan    because he believed the board should have waited until its next    meeting to make a decision. He said that would have given board    members more time to consider the project and allow the newest    member of the board to participate.  
    The projects construction is contingent on the finalization of    a sewer association, which would be responsible for a private    sewer system used by businesses on or near Liberty Lane. Plans    for the hotel and the future site of a neighboring assisted    living facility were put on hold last year when the town and    stakeholders could not come to terms on who would be    responsible for the sewer.  
    In February, selectmen and stakeholders approved documents for    a sewer association proposed by stakeholders and vetted by the    town attorney, allowing construction of the assisted living    facility to move forward. Selectman Jim Waddell, his boards    representative to the Planning Board, asked if representatives    from AG Hampton Hospitality had seen the sewer association    documents and were prepared to be part of the association.  
    Attorney Chris Mulligan, representing AG Hampton Hospitality,    replied his client is on board with the sewer association. He    said the applicants part in the association is still a work in    progress, but he said there appears to be an end in sight.  
    We certainly anticipate that a condition of approval would be    (that) everything is done to the towns satisfaction with    regard to the Liberty Lane sewer association and the easements    that need to be in place, said Mulligan.  
    AG Hampton Hospitality will have five years to complete the    project under the conditions of the Planning Boards approval,    the five-year clock starting when the sewer association is    finalized. Board members said that would prevent the company    from losing time to work in the event the sewer associations    formation is delayed by several months.  
Continue reading here:
New Marriott hotel gains approval - Seacoastonline.com
 
Category 
Office Building Construction | Comments Off on Foundry III rings up one of SF’s highest price-per-sq.-ft. sales – San Francisco Business Times 
    Frank Gehry, the legendary starchitect who designed the Walt    Disney Concert Hall and myriad other Los Angeles landmarks, is    leaving his mark on El Segundos growing creative office    landscape.  
    Construction is underway on an 80,000-square-foot standalone    building designed by Gehry at Utah Avenue and Douglas Street,    part of a campus that was formerly home to Xerox Corp.  
    Set to open by the years end,Ascend at Utah Avenue    Campuswill feature 24-foot clear-height ceilings,    towering glass panel walls and a 16,000-square-foot balcony.  
    Unlike other creative offices taking shape in repurposed    warehouses once used by aerospace and defense manufacturers,    Gehry is starting from scratch, demolishing existing structures    and raising the building onto a podium that will house    ground-level parking.  
    Renderings show a vast open space filled with natural light,    skeletal support beams, lights hanging from exposed high    ceilings and a mix of hip work stations and lounge areas. The    space also can be divided for two 40,000-square-foot tenants.  
    The $50 million project is being developed by NSB Associates, a    Beverly Hills-based commercial real estate firm founded by    Gehrys longtime friend, Larry Field.  
    Freeing space  
    In a video highlighting the project, Gehry said tenants like    creative office space because it offers the freedom of not    being locked into a cubicle.  
    Its not architectural in the sense that youre making an    architectural statement, it is really creating an environment    that energizes and promotes interactivity in a less formal    way, said Gehry, who also designed Facebooks    430,000-square-foot campus in Menlo Park.  
    Seven years ago, Gehry came close to moving his own offices to    El Segundo. He also designed a43,500-square-foot research    and development facilityon the Utah Avenue Campus for    Kite Pharma.  
    In the video, his son, Sam Gehry, called the city an up and    coming area with a nice, sort of small-town feel in LA, but    theres always been sort of these quirky little warehouse    spaces leftover from the aerospace industry kind of moving    out.  
    Utah Avenue Campus promotes its location near Los Angeles    International Airport, the 105 and 405 freeways, and the Metro    Green Line as selling points, as well as the citys    business-friendly reputation.  
    Several years ago, El Segundo embarked on an ambitious    rebranding and marketing effort to draw in tech companies    getting priced out of Silicon Beach, highlighting incentives,    such as lower business tax rates, a streamlined permitting    process and accelerated plan checks.  
    More than 100 companies have opened up shop since in the small    city of 16,500 residents, where the population swells to more    than 70,000 mostly professionals in the daytime.  
    Sending parking underneath the building breaks the mold of a    standard warehouse, Sam Gehry said in the video.  
    Because we had the freedom to break from a traditional    warehouse in the sense that theyre pretty much boxes with no    windows, we were able to incorporate all of the windows into    the facade at this point in the design of the building as well    as a lot of skylights and natural light, he said.  
    A website marketing the property gives visitors a 360-degree    virtual tour of the building and patio.  
    A 'pioneering building'  
    Anthony OCarroll, vice president of NSB Associates, said the    firm originally planned to refurbish a couple existing    buildings it acquired on the site.  
    But when we had the opportunity to work with Frank, he    suggested to us building across those two lots, taking them    down and solving the parking problem by going up, he said. He    thought it would really work here and I think its the first    time Im aware of that this sort of ground-up construction is    being done in El Segundo.  
    NSB Associates began acquiring property in El Segundo 12 years    ago, OCarroll said, and in that time, the city has transformed    from an aerospace hub to a magnet for creative offices. He    called the Ascend project a vote of confidence in the city.  
    Its a kind of pioneering building and it speaks to the way    that El Segundo is going to continue to grow and to develop,    OCarroll said. Theres a lot of interest from real estate    investors and builders down there.  
See the rest here:
Frank Gehry designed this hip, creative office building in El Segundo ... - Beach Reporter
 
Category 
Office Building Construction | Comments Off on Frank Gehry designed this hip, creative office building in El Segundo … – Beach Reporter 
Category 
Office Building Construction | Comments Off on What’s the status on SouthPark new construction, redevelopment projects? – Charlotte Business Journal 
March 22, 2017 08:42 ET    | Source: Nordecon    
      multilang-release    
    Nordecon Betoon O, a    Nordecon Group company, entered into a contract with the    lemiste City developers Mainor lemiste subsidiary piku    Majad O for the construction of a parking house with a space    for 428 cars. The facility will be located adjacent to the    countrys largest office building, pik Building and in the    first phase of the construction a historical Dvigatel    production facility will be enlarged to a five storey 14,000    sqm parking house.  
    The value of the contract is 3.995 million euros plus    value added tax. The construction works will be completed in    summer 2018.  
    Nordecon (www.nordecon.com) is a group of construction    companies whose core business is construction project    management and general contracting in the buildings and    infrastructures segment. Geographically the Group operates in    Estonia, Ukraine, Finland and Sweden. The parent of the Group    is Nordecon AS, a company registered and located in Tallinn,    Estonia. In addition to the parent company, there are more than    10 subsidiaries in the Group. The consolidated unaudited    revenue of the Group in 2016 was 183 million euros. Currently    Nordecon Group employs close to 700 people. Since 18 May 2006    the company's shares have been quoted in the main list of the    NASDAQ Tallinn Stock Exchange.  
    Andri    Hbemgi    Nordecon    AS    Head of    Investor Relations    Tel: +372    6272 022    E-mail:    andri.hobemagi@nordecon.com    http://www.nordecon.com
      Related Articles    
       ESTONIA    
      Nordecon Logo    
      LOGO URL | Copy the link below          
        Formats available:      
Continue reading here:
Construction contract (pik Building parking house) - GlobeNewswire (press release)
 
« old entrysnew entrys »
Page 60«..1020..59606162..7080..»