Construction projects are currently in progress in the Webster City school district. Future projects have been planned and outlined for the summer months.

High school

Terrazzo flooring: Superintendent Mike Sherwood said that the terrazzo flooring is almost complete in the complex addition. It has been laid, poured, ground, sealed and waxed.

Heating and cooling system: Continued work is being done on the system, it has to be finished before the gym floor can be installed. Sherwood said that it should hopefully be finished in the next couple weeks.

Gym floor prep has been completed. The concrete must have a certain variance, and only three or four areas of the floor needed to be ground and filled.

Gym floor installation will start in late March. Sherwood said it will take between 6 and 8 weeks to complete - that includes laying the floor, staining and painting it.

Bleachers are due to arrive in mid-May. Installation will take 4 to 6 weeks, finishing in approximately mid-June.

Tile installation is mostly complete in the bathrooms. The main bathrooms located near the main west entrance have been completed and ceilings are in the process of being installed. Tile work on the bathrooms by the auditorium is nearly completed. Tile work in the connecting hallways by the old locker rooms that connect the new addition is finished.

Ceiling installation in the showers is currently taking place in the locker rooms. The ceilings are hard not drop ceilings.

Work on the parking lots by the high school office, south and main west entrance connecting to Bank Street will start soon. The design for the circle drive near the auditorium entrance has also been approved by the city.