By STAFF REPORT news@saukvalley.com 800-798-4085, ext. 5501

DIXON The streetscape project continues downtown. Heres a summary of work planned for next week, provided by the project engineers:

West of Peoria, on the north side of First Street to Highland Avenue, curb and gutter work and sidewalk installations will close the eastbound lane on First between Peoria and Highland off and on during daytime hours while debris is removed.

The traffic detour will be maintained to South Second Street and then to Peoria Avenue.

On First Street between Peoria and Hennepin, sidewalk and curb and gutter installation on the north side of First also will cause the occasional daytime closures of the eastbound lane on First, between Peoria and Hennepin avenues, also for debris removal.

The removal of storm and sanitary sewer installationswill begin between First Street and Commercial Alley on Peoria.

Peoria Avenue traffic southbound will remain open, with the detour to Highland Avenue.

On Ottawa Avenue, from First to River street, sanitary sewer and water main work will be finished.

On First Street, from Galena to Ottawa avenues, workers will finish sidewalk work and pour concrete pavement from Ottawa to the drive-thru at Fifth Third Bank.

At the intersection of Ottawa and First, brick pavers will be installed at the crosswalks. The intersection will be closed most of the week while the concrete cures.

View post:
Next week's streetscape schedule in Dixon

Related Posts
September 6, 2014 at 4:01 pm by Mr HomeBuilder
Category: Gutter Installation