Reston Association will need to get creative in order to fund its planned renovation of the Lake Thoreau Pool.

The majority of residents who spoke at the associations board of directors meeting on Thursday expressed support for funding the project in 2021 so that it can reopen in 2022 as planned. Membersurging board members to consider a variety of funding and design options if necessary to make it more feasible.

Suggestions included opening the pool up to non-RA members, turning the pool into a shallow-end-only facility to make maintenance easier, and opening up the pool deck year-round so that it could be utilized for other activities.

Now that we are all living through this pandemic, we know the huge importance of outdoor spaces, Giselle Agosto Hincapie, whose family lives in walking distance of the pool, said. The idea of completely eliminating the pool or delaying the construction project is truly disheartening. I think a pool can be incorporated with year-round amenities in this space.

Kimley-Horn, the consultant hired to develop design concepts for the pool project, estimates that its first proposal, a more straightforward renovation that stays within the sites existing footprint, would cost somewhere between $2.9 million and $3.5 million.

This design would install a zero-depth wading pool in what used to be the facilitys deep end, expand the parking lot and bathhouse to meet Fairfax County and Americans with Disabilities Act code requirements, and incorporate an elevated observation and lounge deck.

A second proposal that would involve a more extensive overhaul of the site would cost between $3.8 million and $4.6 million, though Kimle-Horn landscape architect Ron Kagawa says there has been a great preference for the simpler concept.

Kagawa says a significant part of the projects cost is tied to the need to level out the site so that it is more accessible and to construct an approximately 450-foot-long retaining wall along the lakefront and around the parking lot.

Chris Schumaker, Reston Associations senior capital projects operations manager, estimates that if RA picks the first project concept, it would need to commit an additional $3.1 million on top of the $350,000 allocated to the Lake Thoreau project in 2020, possibly splitting the $3.45 million total cost between $1.6 million in 2021 and $1.5 million in 2022.

However, Reston Association also has five other pools and three tennis courts that are expected to need renovations between 2022 and 2031.

Adding these other projects on top of the Lake Thoreau pool funding, the associations repair and replacement reserve fund could drop into a negative balance by 2023 and not recover until 2027, according to Schumakers projections.

A lot of our facilities are nearing that 40, 50-year age mark, Schumaker said. We can safely assume there are going to be some major projects coming down the pike that were going to need to be aware of and planning for.

RAs Board of Directors will discuss options for financing the Lake Thoreau pool renovation in more detail during a special working session on Oct. 8.

Photo via vantagehill/Flickr

See more here:
Lake Thoreau Pool Funding Looms Over Reston Association - Reston Now

Related Posts
September 28, 2020 at 9:00 am by Mr HomeBuilder
Category: Landscape Pool